Sprint planning template

A one-page sprint plan: the goal, who’s available, what’s in, how big each item is, and what could go wrong. Free as a CSV that opens in Google Sheets, Excel and Notion, no sign-up.

Works in Google Sheets, Excel and Notion. Formulas included.

sprint-planning-template.csv
example, filled in
SPRINT 42 · – Goal: admins can invite teammates by email and choose their role.

1 · Capacity

PersonDays availableNotes
Jonas10
Lena10
Sam8On call Tue–Wed
Ken9Conference Fri
Total37At 70% focus: 26 dev-days

3 · Risks and open questions

  • Seat limit policy isn’t decided: block, warn or charge?Billing · Wed
  • Accepting an invite touches sign-in. Spike it first.Ken · Mon

4 · Definition of done

  • Tests pass in CI
  • Behind a feature flag
  • Support and docs notified
  • Demoed to product

2 · Backlog, in dev-days

ItemOwnerBestLikelyWorst
INV-1Invite modal with role pickerSam123
INV-2Invitations API: create, revoke, acceptKen235
INV-3Signed invite tokens with expiryJonas0.512
INV-4Accept-invite page, four statesLena1.52.54
INV-5Seat limit checkUnassigned123
Total610.517

Fits: even the worst case, 17 dev-days, is inside the 26 the team has at 70% focus.

What’s in it

What a sprint plan needs, and nothing else.

Sprint goal

One sentence the team can check every decision against.

Capacity

Who’s around and for how long, with time off and on-call taken out first.

Backlog with ranges

Best, likely and worst case per item, so you can see whether the bad case still fits.

Risks and open questions

Each with an owner and a date. An open question without an owner becomes scope creep.

Definition of done

What “finished” means for every item, agreed before anyone starts.

How to use it

How to run sprint planning with it.

The Scrum Guide timeboxes sprint planning to at most eight hours for a one-month sprint, and less for shorter sprints. Filling in capacity beforehand saves most of that time.

  1. 01Before the meeting: fill in capacity, and have the product owner put the backlog in priority order.
  2. 02Agree the sprint goal in one sentence.
  3. 03Pull items in order and estimate each as a range. Stop when the worst case reaches capacity. Use planning poker if the team disagrees.
  4. 04Write down the risks that came up, each with an owner and a date.

Skip the blank sheet

Let SprintProof fill it in.

Describe the feature and the AI planner drafts the backlog with ranges. The check library fills in the risks you’d otherwise find mid-sprint, and tasks go straight to Jira or Linear.

See how it works

FAQ

Sprint planning questions

What should a sprint plan include?
A sprint goal, the team’s capacity, the backlog items you’re committing to with an estimate for each, the open risks, and a definition of done. That’s everything in this template.
How long should sprint planning take?
The Scrum Guide sets a maximum of eight hours for a one-month sprint. Shorter sprints get a shorter meeting.
Why ranges instead of story points?
Points work for comparing items. A range in days shows whether the bad case still fits the sprint. You can use both: see the story points guide.
How do I open the template in Google Sheets, Excel or Notion?
Download the CSV. In Google Sheets choose File, Import, Upload. Excel opens it directly. In Notion choose Import, CSV. The totals are formulas, so they keep working when you change the numbers.

Team

Plan the next sprint with ranges.

Create your account and name your workspace. Your first feature plan is free. To keep planning, subscribe to Team: the 14-day money-back guarantee applies.

Want to hear when the ChatGPT and Codex plugin ships? Leave your email.

Team size (optional)
One email when it ships. No spam.